Page 248 - IRSEM_Main Book
P. 248

(h) After  the  contractor's  dated  signature  has  been  obtained,  the  official
                            recording the measurements shall attest his full signature and designation
                            at  the  end  of  the  measurements.  RTGS/NEFT  – mandate  Form must be
                            collected.

               10.3.4   'On Account' Measurements

                        (a) For measurements against which on account bills are prepared and which
                            are  subject  to  adjustment  in  final  bills,  the  official  incharge  may  use
                            percentage measurements for the part the work completed.

                        (b) Quantities  for  payment'  on  account'  shall  never  exceed  the  estimated
                            quantities of actual work done upto the time of payment. In order to ensure
                            this, the following certificate shall be recorded by the official incharge in the
                            measurement book for all' on account' measurements.

                            "I hereby certify that not less than the quantity of work paid for has actually
                            been  done  and  that  the  measurements  are  from  plans/approximately
                            estimated".

               10.3.5  Responsibility of the Assistant/Divisional Signal and Telecommunication
                        Engineer for Measurements of Works

                        The  Assistant/Divisional  Signal  and  Telecommunication  Engineer  shall  be
                        responsible for the correctness of the measurements Quantity and adherence
                        to clauses & specifications laid down in the contract for all works in his charge.
                        He  shall  ensure  that  the  measurements  are  made  Timely  in  the  specified
                        manner and recorded by the SSE/JE(Signal)/incharge of the work. Test check
                        of  works  as  per  extant  norms  shall  be  done  by  ASTE/DSTE  and  recorded,
                        accordingly on the measurement book.


               10.3.6  Computation of Quantities

                        After measurements for a work are recorded, the quantities shall be computed
                        and entered in the 'contents' column of the measurement book. This may be
                        done by the official recording the measurements himself or in the office.


               10.3.7  Preparation of Abstracts in Measurements Books

                        (a) After  the  quantities  are  computed,  an  abstract  shall  be  prepared  in  the
                            measurement book in the office of Sr. Divisional Signal and Telecommunication
                            Engineer/Dy Chief Signal and Telecommunication Engineer. The abstract
                            shall be headed thus "Abstract of pages............to...........". The abstract shall
                            show the correct description of the item, total quantity done up-to-date, rate
                            and the total value for each item measured/checked, in connection with the
                            work. The total of the values of all the items will be the total value of the work
                            done up-to-date.

                        (b) In the case of a first and final bill, this amount will not be subject to any
                            deduction and will be paid in full to the contractor, except Security Deposit
                            and other taxes.




                                                  Chapter 10: Contracts for Works                 Page 214 of 535
   243   244   245   246   247   248   249   250   251   252   253