(c) In the case of an 'on account' bill, the prescribed percentage of the value of
                            the  work  done  since  the  last  certificate  shall  be  deducted  as  security
                            deposit towards the due fulfillment of the contract. The balance will be the
                            amount payable to the Contractor and this amount must be written clearly
                            in words as well as in figures.

                        (d) On satisfactory completion of the work, the security deposit will be refunded
                            to the contractor after the final payment for the work is made. Part of the
                            security deposit may be kept with the Railway in specified cases whenever
                            it is necessary to watch the results of the work and to ensure that there will
                            be no failure of the work for the period stipulated in the contract.


                        (e) The abstract shall be signed and dated by the Assistant/Divisional Signal
                            and Telecommunication Engineer.


                        (f)  Each paragraph of the measurement book to which the  abstract pertains
                            shall be crossed in Red Ink diagonally thus.


                        (g) See Abstract pages …………………


                        (h) At the foot of each abstract the relevant bill number and date of preparation
                            of the bill shall be entered.

               10.3.8  Submission of Bills: After the abstract is prepared in the measurement book,
                        the bill shall be prepared in the Sr. Divisional Signal and Telecommunication
                        Engineer's/Dy. Chief Signal and Telecommunication Engineer's Office on the
                        prescribed form or submitted by firm.

               10.3.9  Checking of Bills

                        (a) The quantities in measurement books submitted by the Assistant Signal and
                            Telecommunication  Engineer/Divisional  Signal  and  Telecommunication
                            Engineer shall be checked for arithmetical accuracy in the Sr. Divisional Signal
                            and Telecommunication Engineer's/Dy. Chief Signal and Telecommunication
                            Engineer Office where it will be verified that;


                            (i)  The description of items is according to the contract schedule.


                            (ii) There are no delays in recording measurements.


                            (iii) The quantities executed are according to sanctioned plans and estimates.

                            (iv) Where  measurements  are  not  recorded,  correct  reference  to  the
                               standard measurements is clearly given, and


                            (v) The  quantities  recorded  in  the  bill  agree  with  those  shown  in  the
                               measurement  book  and  rates  higher  than  those  sanctioned  are  not
                               allowed.