(b) An endorsement shall be made at the end of Assistant/Divisional Signal and
                            Telecommunication Engineer's abstract in the measurement book under the
                            signature of Sr. Divisional Signal and Telecommunication Engineer/Dy. Chief
                            Signal and Telecommunication Engineer giving reference to the particulars
                            of the bill passed.

                        (c) RTGS/NEFT mandate form shall be obtained from contractor for enabling
                            electronic payments.


                        (d) The Railway Administration may lay down a time schedule for preparation
                            and checking of bills.

               10.3.10 Bill Registers


                        The Sr. Divisional Signal and Telecommunication Engineer's/Dy. Chief Signal
                        and Telecommunication Engineer’s Office shall maintain Bill Registers in which
                        all bills prepared in their office shall be recorded. The Register shall be kept
                        upto  date  and  complete  information  with  reference  to  agreements,  work
                        orders, abstracts in measurement books and amounts.

               10.3.11 Disputes with Contractors

                        Every effort must be made to ensure supply of drawings, handing over of site,
                        deputing  of  staff  for  supervision,  materials  (if  any),  budget  for  work,  Timely
                        payments to contractor, to avoid disputes with the contractor.


                        (a) On the completion of every work, 'No claims certificate' shall be obtained
                            from  the  Contractor  according  to  the  relevant  clause  or  clauses  in  the
                            condition of contract. Every month or when 'on account' bills are made out,
                            the contractor shall be instructed to submit a list of outstanding claims, if any.


                        (b) If  there  is  any  likelihood  of  a  dispute  with  a  contractor,  all  documents,
                            measurements and letters bearing on the case shall be at once collected
                            and stored in safe custody with the officer responsible for the case. In all
                            such cases care shall be taken to commence all correspondence with the
                            contractor  with  head  line  'without  prejudice'.  The  contractor  shall  be
                            instructed  to  submit  complete  details  of  his  claims  in  writing  with  a
                            certificate to the effect that these are final.


                        (c) In spite of all reasonable efforts as per agreement, if the contractor refuses
                            to  sign  the  final  contract  certificate,  the  final  contract  certificate  shall  be
                            forwarded  to the  Accounts  Officer  to  make payment. The  contractor may
                            accept payment, if he wishes under protest.


                        (d) Disputes arising out of the contract for a work, between the contractor on
                            the one hand and the Railway Administration on the other, shall be referred
                            for  arbitration  in  accordance  with  the  relevant  clause  in  the  General
                            Conditions of Contract.