(b) Ordinarily the lowest eligible tender may be accepted by the Railway unless
                            such acceptances would not be in the public interest. The  acceptance or
                            rejection  of  any  tender  is  left  entirely  to  the  discretion  of  the  authority
                            empowered to deal with the matter and no explanation can be demanded
                            by any tenderer as to the cause of rejection of his tender.


               10.2.8  Entering  into  Contracts:  No  contract  shall  be  entered  into  unless  authority
                        exists for commencement of the work. No authority shall enter into a contract
                        beyond its own powers of sanction.


               10.2.9  Execution of Contract Documents

                        (a) The tenderer whose tender is accepted shall be required to appear at the
                            office  of  the  concerned  Chief  Signal  and  Telecommunication  Engineer/
                            Construction/Projects  or  Sr.  Divisional  Signal  and  Telecommunication
                            Engineer/Dy.  Chief  Signal  and  Telecommunication  Engineer  as  the  case
                            may be, in person or if a firm or corporation, a duly authorised representative
                            shall  so  appear,  and  execute  the  contract  within  stipulated  time  period.
                            Failure to do so shall constitute a breach of the agreement effected by the
                            acceptance of the tender in which case the earnest money accompanying
                            the tender may be forfeited.

                        (b) In the event of any tenderer, whose tender is accepted, refusing to execute
                            the  contract  documents  the  authority  may  determine  that  such  Tenderer
                            has abandoned the contract and thereupon his tender and the acceptance
                            thereof  shall  be  null  and  void  and  the  earnest  money  accompanying  the
                            tender shall be forfeited.

               10.2.10 Form of Contract Documents

                        (a) Every contract shall be complete in respect of the documents it constitutes.

                        (b) The contract agreement required to be executed by the successful tenderer
                            shall be in the form prescribed by the Administration for the purpose. The
                            draft of the contract agreement shall be vetted by the Accounts Department.

               10.2.11 Copies of Contract Documents

                        (a) Sufficient number of copies of the contract documents shall be available for
                            use in the offices of the Sr Divisional Signal and Telecommunication Engineer/
                            Dy. Chief Signal and Telecommunication Engineer and the SSE/JE (Signal)/
                            incharge.  If  materials  are  to  be  inspected  by  an  agency  other  than  the
                            consignee,  a  copy  of  the  contract  documents  shall  be  supplied  to  the
                            inspecting agency also. No deviations in the contract documents shall be
                            permitted without the sanction of the competent authority.

                        (b) The executive Officers and incharge supervisor shall thoroughly study the
                            contract  documents  for  works  to  be  carried  out  and  shall  adhere  to  the
                            provisions contained therein.







                                                  Chapter 10: Contracts for Works                 Page 211 of 535