10.3.12 Completion Reports
(a) After completion of a work as per its scope, Completion report shall be
drawn by the Sr. DSTE/Dy. CSTE incharge of the work. All expenditures
like stores, contract, adjustment memos, work shop debits, D&G charges
etc., shall be properly accounted.
(b) Finance concurrence of Completion estimate shall be obtained from
associated finance and sanction from the competent authority.
(c) Work shall be deleted from list of the works and same shall be intimated to
PCSTE/CSTE(C).