Chapter 9: Procedure for Commissioning of Signalling
                                                    Installations


                                             Section 1: General Instructions


               9.1.1  Reference to Rules

                       (a) The safety of the travelling public is ensured by the Rules laid down in

                          (i)  The Indian Railway Act.

                          (ii)  The General Rules & Subsidiary rules for all Open Line Railways.

                          (iii)  The Rules for Opening of a Railway or section of a Railway for the public
                               carriage of passengers.

                          (iv)  The Indian Railway Schedule of Dimensions.

                       (b) The rules provide for the legal authorisation that shall be obtained for any
                          work which affects the running line, before the work is started or brought into
                          use and before a new section of a line is opened for public traffic.

               9.1.2  Notification to Railway officials  before opening works: No signalling  work
                       affecting the running of trains or working of traffic at a station shall be brought
                       into use, until staff of all concerned Departments have been notified by means
                       of a circular issued by the Operating Department Timely intimation of the date of
                       commencement of work, duration  of work, arrangements for working of trains
                       during the progress of the work, date of opening of work, etc. shall be given to
                       the  Operating  Department,  whenever  any  new  or  revised  traffic  working
                       instructions are to be brought into use to enable operating Department to give
                       the station and running staff due notice.

               9.1.3  Approved plans, Drawings and Specifications: All works shall be carried out
                       strictly in accordance with the approved plans, standard drawings and specifications
                       and should conform to the provisions of this manual where such are applicable.
                       Deviations, if any, shall have the prior approval of the Principal Chief Signal and
                       Telecommunication Engineer. All deviations shall be marked on the completion
                       drawings and forwarded to  the Principal Chief Signal and Telecommunication
                       Engineer for correction of the tracings and issue of revised prints.