Section 2: Obtaining Sanction for Works on Lines Opened to
                                                             Traffic

               9.2.1  Works Requiring Notice to and Sanction of the Commissioner of Railway
                       Safety

                       Under Section 20 of the Indian Railways Act and Chapter VI, VII of the "Rules
                       for  the  Opening  of  a  Railway  or  Section  of  a  Railway  for  public  Carriage  of
                       Passengers" the approval of Commissioner of Railway Safety is required for the
                       execution of any work on the open line which will affect running of passenger
                       trains and any temporary arrangement necessary, for carrying it out, except in
                       cases of emergency.

                       The following signal and interlocking works, when they are connected with or
                       form part of a Railway already opened for carriage of passengers require the
                       sanction  of  Commissioner  of  Railway  Safety,  before  they  are  commenced  or
                       opened:


                       (a) Additions/extensions or alterations to existing Block, Signalling and interlocking
                          installations.


                       (b) Change in block, Signalling and Interlocking scheme.

                       (c) New stations temporary or permanent.

                       (d) Interlocking of level crossing, catch siding and slip sidings etc.

                       (e) Closing  of  Manned  Level  Crossing  gates  after  approval  of  district
                          administration obtained by Engineering department.

               9.2.2  The  following  works  shall,  which  enhance  level  of  safety,  however,  do  not
                       require the sanction of the Commissioner of Railway Safety:

                       (a) Provision of Telephones at already manned level crossings.

                       (b) Provision  of  electrical  &  mechanical  lifting  barrier  including  emergency
                          interlocking arrangements, sliding boom at already interlocked Level Crossing
                          Gates.

                       (c) Interlocking of existing LC Gates within already existing interlocked station
                          yard by existing signals in the same or shifted location.

                       (d) Provision  of  all  categories  of  track  circuits,  axle  counters  including  dual
                          detection.

                       (e) Replacement/Modification  of  signalling  assets  without  any  change  in  the
                          yard layout or signal interlocking scheme either in station or at mid section
                          Level Crossing Gates.


                       (f)  Replacement of Block instruments by any other approved type of instrument
                          or provision of block proving through Axle counters or Track Circuiting using
                          existing Block instruments.