(g) The replacement of block instrument  without any change in the system of
                          block working.

                       (h) Providing Electronic Interlocking/Panel Interlocking/Route Relay Interlocking
                          or alterations there of in Non-passenger Line section.


                       (i)  Changing  from  Control  Panel  to  Control  Terminal/VDU  in  Electronic
                          Interlocking.

               9.2.3  Personal  approval  of  the  PCSTE  will  be  required  for  sanction  of  the  works
                       mentioned at Para 9.2.2.


                       PCSTE of Railway shall submit Safety certificates & quarterly statement of all
                       such sanctions accorded by him to the concerned CRS, PCSTE's sanctions are
                       not given in a routine manner but following laid down procedure.

                       It is therefore, suggested that while giving sanctions by PCSTEs, following must
                       be ensured:

                       (a) All  relevant  documents  that  are  prepared  by  field  units  (for  submission  to
                           CRS for his sanction) for commissioning of the works would be submitted to
                           PCSTE  for  his  sanction. This  includes Engineering  scale/Signalling  Plans,
                           SWR diagrams and SWR.


                       (b) Application in format as per Annexure: 9-A8 shall be submitted duly signed
                          by JA grade officer, incharge of the work for applying for PCSTE's sanctions.
                          Similarly,  PCSTE's  sanction  shall  also  be  communicated  in  the  defined
                          format enclosed as Annexure: 9-A9.

                       (c) Application  for  CSTE's  sanction  received  in  Head  quarter’s  office  shall  be
                          scrutinised  as  per  the  check  list  laid  down  as  Annexure:  9-A10  by  Dy.
                          CSTE/Incharge of design or CSTE (planning) and put up for sanction of the
                          PCSTE.

                       (d) Personal  sanction  of  PCSTEs  would  be  required  and  it  shall  not  be
                          delegated to any lower level.

                       (e) Sanctions  would  be  recorded  by  PCSTEs  as  a  numbered  sanction
                          maintaining  a  register  for  the  same  similar  to  sanction  numbers  being
                          maintained by CRS.

                       (f)  The validity of the PCSTE's sanction shall be for a period of six months. Re-
                          validation of the sanction after six months may be considered based on valid
                          reasons.











                                    Chapter 9: Procedure for Commissioning of Signalling Installations   Page 186 of 535