(b) Before signing the Safety Certificate the Engineer-incharge shall,

                          (i)  Test the new works and see that installation has been carried out correctly.

                          (ii) Fully satisfy himself, that the work can be opened for the public carriage
                              of passengers without endangering the safety of the travelling public or of
                              the employees of the Railway.

                       (c) After fully satisfying himself, he shall bring the installation into use by issuing
                          a message in the form given on the sanction Application (Annexure: 9-A1) to
                          the Commissioner of Railway Safety with copy to all concerned.


                       (d) In case of joint works, the message shall also be signed by the Engineer-
                          incharge of the concerned Departments for their portion of the work.


                       (e) The Safety Certificate shall be countersigned by the Officers, who had applied
                          for the sanction of Commissioner of Railway Safety/PCSTE. A certificate from
                          Operating Department, stating that the necessary Station Working Rules have
                          been  issued  and  giving  reference  to  sanction  of  deviations  (if  any)  from
                          General and Subsidiary Rules, shall also be attached.

                       (f)  Copies  of  the  Safety  Certificates  shall  be  sent  to  the  Divisional  Railway
                          Manager  and  the  Principal  Chief  Signal  and  Telecommunication  Engineer
                          and also to the Principal Chief Engineer/Principal Chief Electrical Engineer if
                          the Engineering/Electrical Department is/are involved in the work.

                                        Section 3: New Lines & Electrification


               9.3.1  Application to the Commissioner of Railway Safety

                       (a) In the case of new lines or electrification, prior sanction of the Commissioner
                          of Railway Safety for commencement of the work is not necessary but when
                          it  is  proposed  to  open  the  line  for  passenger  traffic  or  to  initiate  electric
                          traction  on  a  line  already  opened,  the  following  documents  are  to  be
                          furnished  by  the  General  Manager  of  Railway  to  the  Commissioner  of
                          Railway  Safety  at  least  one  month  before  the  date  by  which  the  line  is
                          expected to be ready for opening.

                          These documents collectively are termed as the Opening Documents.

                          (i)   Tabulated details.

                          (ii)  Index plan and section of Railway.

                          (iii)  Drawings of works.

                          (iv)  List of questions and answers duly filled in.

                          (v)  Certificates.

                          (vi)  List of infringements of maximum and minimum dimensions.

                          (vii)  Diagram of proposed testing train.

                          (viii) Station working rules to be enforced at each station.