3.6.4  Progress Report of Works

                        The  SSE(Signal)/Incharge  of  works  shall  submit  a  Progress  Report,  every
                        month of all the works in his charge  to the  Dy.CSTE  (Construction) as per
                        Annexure: 3-A7 which shall include:

                        (a) The progress of work and probable date of completion

                        (b) Reference  to  requisitions  or  work  orders  against  which  supply  has  not
                            been  made;  also  details  of  items  which  are  particularly  required  and  on
                            account of which works are being delayed
                        (c) Delays arising from other causes


                3.6.5  Opening of Works
                        (a) The  SSE(Signal)/Incharge  of  works  shall  advise  the  Sr.  DSTE/Dy.CSTE
                            (Construction),  when  a  work  will  be  ready  for  opening,  in  order  that  the
                            latter may arrange for fixing of a date and for the issue of the necessary
                            notices.

                        (b) When a new work or alteration to an existing work is about to be brought
                            into  service,  the  SSE(Signal)/Incharge  shall  ensure  that  approved  plans,
                            Control  Table,  circuit  diagrams,  CRS/PCSTE  sanctions,  required
                            approvals, OEM test certificates of equipments, FAT/SAT Testing reports
                            etc. are available before commissioning/opening (Refer Annexure: 21-A2).
                            If there are minor alterations, the existing diagrams may be corrected and
                            endorsement  made  by  the  SSE(Signal)/Incharge  duly  advising  HQ  for
                            updating their records.

                3.6.6  Completion Certificate and Completion Report

                        (a) The  SSE(Signal)/Incharge  shall  submit  a  Completion  Certificate  to  the
                            Sr.DSTE/Dy.CSTE (Construction) as per Annexure: 3-A8 immediately, after
                            a  new  work/alteration  to  an  existing  installation  has  been  brought  into
                            service.

                        (b) The  SSE(Signal)/Incharge  of  the  works  shall,  immediately  after  the
                            completion of a work submit a Completion Report to the officer Incharge
                            which shall contain the following:

                            (i)  List of all materials received from the stores and other sources with all
                                particulars.

                            (ii)  List of all materials used for the work.
                            (iii)  List of materials released and returned to stores with particulars.

                            (iv)  List of excess materials returned to stores with particulars.

                            (v)  Details of contractor(s), who executed the works.

                            (vi)  Special problems or difficulties experienced during the execution of the
                                work (if any) and

                            (vii) Transfer  unutilised  materials  from  'Works  Registers'  of  that  work  to
                                other works to get the credit for that work.