(b) The  SSE(Signal)/Incharge  taking  over  and  handing  over  shall  inspect  all
                            important works in progress, check the staff and their tools and plants and
                            materials-at-site.

                        (c) The  relieving  SSE(Signal)/Incharge  shall  examine  all  Office  records  and
                            ledgers and initial them with date.

                        (d) Handing over charge statement shall be jointly signed by the supervisors
                            taking over and  handing over and a copy submitted to the Sr. Divisional
                            Signal and Telecommunication Engineer. Errors and discrepancies noted
                            during handing over and taking over, shall be recorded on the statement
                            for  the  information  of  the  Sr.  Divisional  Signal  and  Telecommunication
                            Engineer.
                          Section 6:  Additional Instructions for SSE (Signal)/Incharge

                                                         Construction

                3.6.1  Code Rules: The rules for the execution of works are contained in Chapter 9
                        of  SEM  and  Chapter  XI  of  the  Indian  Railway  Code  for  the  Engineering
                        Department.

                3.6.2  Applicability  of  Rules:  The  instructions  for  SSE(Signal)/Incharge  of
                        construction  will  also  apply  to  SSE(Signal)/Incharge  of  maintenance  when
                        executing  works.  Similarly  the  instructions  for  SSE(Signal)/Incharge  of
                        maintenance  will  apply  to  SSE(Signal)/Incharge  of  Construction  when
                        maintaining equipments at a station.

                3.6.3  Commencement/Execution of Works

                        (a) The instructions contained in Para No. 9.1.4 shall be observed.

                        (b) When  the  estimate  for  a  new  work  is  sanctioned,  the  SSE
                            (Signal)/Incharge shall submit requisitions for the  materials without delay
                            and  ensure  that  all  the  required  materials  are  made  available.  No  work
                            shall  be  physically  commenced  until  it  is  authorised  by  the  concerned
                            officer.

                        (c) No  work  affecting  an  existing  signalling  and  interlocking  system  shall be
                            commenced,  unless  all  prior/pre  non-interlocking  works  have  been
                            completed, so that the duration of non-interlocking/disconnection will be as
                            short as possible.

                        (d) Location of signals (new or proposed for shifting) shall be jointly surveyed
                            by a Signal Sighting Committee consisting of (i) SSE(Signal)/Incharge, (ii)
                            SSE(Loco)/ and (iii) Traffic supervisors, keeping in view extant instructions
                            and  schedule  of dimensions.  Signal  Sighting  Committee  reports  shall be
                            submitted  as  per  Annexure:19-A1  to  the  Dy.CSTE  (Construction)/
                            Sr.Divisional Signal and Telecommunication Engineer.

                        (e) Introduction  of  a  new  signal  or  alteration  to  an  existing  signal  shall  be
                            taken on hand only after publication of the Traffic Notice.