Page 371 - IRSEM_Main Book
P. 371

(f)  During excavation, the soil of the trenches should not be thrown on the ballast.
                           The soil should be thrown by the side of the trenches away from the track.

                       (g)  In places where cables to be laid within 1 meter from sleeper end, digging
                           beyond  0.50  meter  shall  be  done  in  the  presence  of  an  official  from
                           Engineering Department, and the laying of the cable and refilling of trench
                           should be done with least delay.

                       (h)  The work shall be supervised at site personally by an official of the Signal and
                           Telecommunication Department not below the rank of a JE/SSE (Signal).

                                          Section 3: Cable Laying in RE Area

                15.3.1 Only  unscreened  approved  type  underground  cables  shall  be  used  for
                       signalling purposes.

                       The following precautions shall be taken:
                       (a)  The cable shall be so laid that it is not less than one meter from the nearest
                           edge  of  the  mast  supporting  the  catenary  or  any  other  live  conductor,
                           provided  the  depth  of  the  cable  does  not  exceed  0.5  meters.  When  the
                           cable  is  laid  at  a  depth  greater  than  0.5  meters,  a  minimum  distance  of
                           3 meters between the cable and the nearest edge of the O.H.E structure
                           shall be maintained. If it is difficult to maintain these distances, the  cable
                           shall be laid in DWC-HDPE/Concrete Ducts or any other approved means
                           for  a  distance  of  3  meters  on  either  side  of  the  Mast. When  so  laid,  the
                           distance between the cable and the mast may be reduced to 0.5 meters.
                           These precautions are necessary to avoid damage to the cable in the event
                           of the failure of an overhead insulator.

                       (b)  In the vicinity of traction sub stations and feeding posts, the cable shall be
                           at  least  one  metre  away  from  any  metallic  part  of  the  O.H.E  and  other
                           equipment at the substation, which is fixed on the ground, and at least one
                           metre away from the substation earthing. As far as possible, the cable shall
                           be laid on the side of the track opposite to the feeding post. In addition, the
                           cable shall be laid in concrete or DWC-HDPE pipes (approved type)/Split
                           RCC pipes or other approved means for a length of 300 meters on either
                           side of the feeding point.

                       (c)  In the vicinity of the switching stations, the cable shall be laid at least one
                           metre  away  from  any  metallic  body  of  the  station,  which  is  fixed  in  the
                           ground, and at least 5 meters away from the station Earthing. The distance
                           of 5 meters may be reduced to one metre provided the cables are laid in
                           concrete  pipes/DWC-HDPE-pipes  of  approve  type/ducts  or  any  other
                           approved means.

                       (d)  Where an independent Earth is provided for an O.H.E structure, i.e. where
                           the mast is connected to a separate Earth instead of being connected to
                           the rail, the cables shall be laid at least one metre away from the Earth.

                       (e)  Where there are O.H.E structures along the cable route, the cable trenches
                           shall  as  far  as  possible,  be  dug  not  less  than  5.5  meters  away  from  the
                           centre of the nearest Track.




                                                       Chapter 15: Cables                         Page 319 of 535
   366   367   368   369   370   371   372   373   374   375   376