(i)  In case of Tunnel, provision of cable duct should form part of the Tunnel
                           design.

                       (j)  Provision of suitable duct/pipe/other arrangements shall be incorporated in
                           the bridge design itself for laying of cables on bridges.

                15.1.3 Storage and Transportation of Cable

                       (a)  Cable drums shall not be stacked on flat side. Suitable stoppers shall be
                           placed for stability.

                       (b)  Cable drums shall have access for lifting and moving.

                       (c)  When rolling the cable drum either for unloading or transportation, the drum
                           shall always be rotated in the direction of the ‘arrow’ which is marked on the
                           drum.

                       (d)  The drums shall not be rolled over objects that could cause damage to the
                           protective battens of the cable.

                       (e)  When  unloading  is  carried  out  from  the  vehicle,  the  drum  shall  not  be
                           dropped on the ground directly to avoid damage due to impact. Fork lifter or
                           ramp shall be used.

                       (f)  During all stages of storage, it is essential that the ends of the cable are
                           effectively  sealed  by  end  cap  or  in  any  other  approved  manner  to  avoid
                           water entry into the cable.

                       (g)  It  is  desirable  that  cable  drums  are  stored  in  covered  shed  to  protect
                           against direct exposure to sun.

                              Section 2: Paying Out, Trenching & Laying of Cables

                15.2.1 Paying Out and Testing  of Cable

                       (a)  For paying out cables, the cable drums shall be mounted on cable wheels.
                           It should be ensured that no kink is formed while paying out the cable.

                       (b)  The drum on the wheel shall be brought to one end of the trench, the end of
                           the cable freed and the cable shall be laid along the trench.

                       (c)  A party of labourers shall move along the trench carrying cable at suitable
                           intervals so that cable is not damaged due to dragging along the ground or
                           bent unduly.

                       (d)  Before the cable is laid in the trench, a visual inspection of cable shall be
                           made  to  see  that  there  is  no  damage  to  the  cable.  It  shall  be  tested  for
                           insulation and continuity of the cores. Thereafter the cable shall be laid in
                           the trench. Record of insulation and loop resistance must be maintained.

                       (e)  In cases where the wheels are not available, the drum shall be mounted on
                           an  axle  at  one  end  of  the  trench  and  cable  paid  out  and  carried  by
                           labourers.

                       (f)  In no case, shall the drum be rolled off on to the road for laying the cable
                           and the cable dragged on the ground for laying purposes.