Page 368 - IRSEM_Main Book
P. 368

(g)  Whenever mechanized equipment is used, the work shall be carried out by
                           a trained operator under the supervision of SSE/JE(Signal),  incharge of the
                           work.

                       (h)  Where the cable drum is in damaged condition the cable may be placed on
                           a horizontal revolving platform and the cable paid out in the same manner
                           as given in paras above.

                       (i)  Paying out of cable should be done by rotating the cable drum and not by
                           pulling the cable with excessive force.

                15.2.2 Trenching

                       (a)  The width of cable trenches should commensurate with number of cables.
                           The minimum width shall be kept as 0.3 meters. The bottom of the cable
                           trench  should  be  levelled  and  got  rid  of  any  sharp  materials.  In  the  soft
                           ground,  the  cable  should  be  laid  at  the  bottom  of  the  trench  previously
                           levelled. In the rocky ground, the cable should be laid on a layer of sand or
                           sifted earth of 0.05 meters thickness previously deposited at the bottom of
                           the  trench.  In  both  the  above  cases,  the  cable  should  be  covered  with  a
                           layer  of  sand  or  sifted  earth  of  0.10  meters  thickness  and  thereafter  a
                           protective cover of trough or a layer of bricks or split DWC-HDPE pipe of
                           approved type or any other approved means should be placed.

                       (b)  Bottom of Trench shall be cleared in such a way, so as to remove all the
                           boulders having sharp edges. In rocky soil, the bottom of the trench shall be
                           filled with river sand or any other soft material and cable shall be laid on
                           smooth surface.

                       (c)  In block section  horizontal directional drilling method  may also be used based
                           on site conditions for the laying of Quad and OFC cables across  the track  at
                           sufficient depth to avoid damage due to future work of doubling etc.

                       (d)  Where  it  is  not  feasible  to  achieve  required  depth  due  to  rocky  soil/other
                           obstructions, protective measures as shown in Drg. No.15-D2 shall be taken.
                       (e)  Where feasible, trenching may be done with suitable machinery, with due
                           precautions  towards  safety  of  the  running  trains.  For  carrying  out  such
                           works, the rules governing the working of machinery along the track shall
                           be followed scrupulously. Suitable instructions in this regard shall be issued
                           by the Railways in the form of a joint circular.

                15.2.3 Laying Of Cables

                       (a)  Cables  shall  be  laid  generally  as  per  instructions  given  in  this  chapter.
                           However, special precautions to be taken in the station yards etc., where a
                           number of other utilities may be existing, may be detailed in a joint circular
                           issued by the Civil Engineering, Signalling and Electrical Department(where
                           applicable) of the Railway.

                       (b)  Cables may be laid underground, either in the trench, in ducts, in cement
                           troughs, in pipes or in any other approved manner.







                                                       Chapter 15: Cables                         Page 316 of 535
   363   364   365   366   367   368   369   370   371   372   373