Para No. 9.2.3(b)                                                              Annexure: 9-A8

                                            Application for PCSTE Sanction

                 No…………………………………………                                               Office……………………


                 From,                                                             Dated…………………..

                      The …………………..

                      Designation…………..

                 To,
                      The Principal Chief Signal& Telecommunication Engineer,

                      …………………………………………………………..

                 Sir,
                      I hereby apply for your sanction to __________________________________________
                 ___________________________________  being  commissioned  and  opened  for  public
                 carriage of passengers when ready as CRS sanction is not required as per para 9.2.2 of SEM.

                 The documents are enclosed as per checklist (Annexure: 9-A10)

                 Modus Operandi

                 The  work………………………………………………..shall  be  carried  out  after  disconnection/non-
                 interlock & traffic block if required at site. After completion of the work reconnection memo
                 shall  be  issued.  The  work  will  be  commissioned  by………………………………  on  receipt  of  the
                 PCSTE sanction and after signing the safety certificate and when required, also dispatch a
                 communication to your address intimating that the work has been opened and the safety
                 certificate signed and issued.


                                                                              Yours faithfully
                                                                              Signature……………

                                                                              Designation………….
                                                                              Dated………….
















                                    Chapter 9: Procedure for Commissioning of Signalling Installations   Page 205 of 535