Para no. 9.3.1(b) Annexure: 9-A5
Safety Certificate for S&T Works for Introducing Electrification
It is hereby certified that the Signalling and Telecommunication works to be executed for the
purpose of introduction of 25 KV single phase, 50 cycles A.C. traction between …………….. and
………………… on …………… Railway have been carried out properly and that electric traction
can be introduced for public carriage of passengers without endangering the safety of the
travelling public or of the employees of the Railway.
Signature
Name
Designation
Chapter 9: Procedure for Commissioning of Signalling Installations Page 199 of 535