Page 22 - IRSEM_Main Book
P. 22

1.1.3  Construction Organisation/Project Organisation/RE Organisation

                        (a) The  expression  “Chief  Signal  and  Telecommunication  Engineer
                            (Construction)”  wherever  used  in  this  Manual  shall  also  include
                            CSTE/Projects,  CSTE/Works,  CSTE/CORE  or  any  other  post  in  Indian
                            Railways in equivalent or higher grade (SAG/HAG) created for execution of
                            works. The Chief Signal and Telecommunication Engineer (Construction)
                            shall  provide  necessary  direction  and  control  for  the  efficient  and  cost
                            effective execution of all works under his charge.


                        (b) The  Chief  Signal  and  Telecommunication  Engineer  (Construction)  may  be
                            assisted at the Headquarters by a team of officers of the level of Deputy Chief
                            Signal  and  Telecommunication  Engineer/Engineers,  Senior  Signal  and
                            Telecommunication  Engineers,  Assistant  Signal  and  Telecommunication
                            Engineers as required.

                        (c) The  Chief  Signal  and  Telecommunication  Engineer  (Construction)  shall
                            maintain  liaison  with  the  Open  Line  Organisation  and  shall  follow  the
                            general  policies  and  procedure  laid  down  for  the  execution  of  works.  In
                            cases  where  a  different  policy  or  procedure  becomes  necessary  to  be
                            followed,  he  shall  do  so  after  due  consultation  with  the  Open  Line
                            Organisation to adopt an accepted policy or procedure.


                        (d) The  Chief  Signal  and  Telecommunication  Engineer  (Construction)  shall
                            exercise necessary budgetary control within the allotment of funds at his
                            disposal and shall co-ordinate with Head  of Construction Organisation for
                            compilation of budget at every budgetary stage.

                        (e) The Chief Signal and Telecommunication Engineer (Construction) shall co-
                            ordinate with the Principal  Chief Signal and Telecommunication Engineer
                            with  regards  to  the  placement  of  personnel  for  the  various  assignments
                            under his charge keeping in view the overall career development of such
                            personnel.

                        (f)  In the case of certain major joint projects for Survey, or construction, the
                            Signal and Telecommunication unit may be constituted as a self-contained
                            unit under the administrative control of the head of the Project.

                        (g) In such cases, the Head of the Signal and Telecommunication Unit shall be
                            responsible  for  co-ordination  with  the  Principal  Chief  Signal  and
                            Telecommunication  Engineer  as  mentioned  in  paragraphs  1.1.3  (c)  and
                            1.1.3 (e).

                        Note: These instructions for construction organisation with suitable modification will
                        apply to the other Heads of the department (HODs) in Signal & Telecom departments
                        when entrusted with specific execution of works.










                                    Chapter 1: Organisation Of The Signal & Telecommunication Department   Page 2 of 535
   17   18   19   20   21   22   23   24   25   26   27