Page 466 - IRSEM_Main Book
P. 466
Note: This Chapter has under mentioned Annexures
S.No. Annexure No. Description
1 19-A1 Signal Sighting Committee Report - For Shifting of Existing Signals/
Erection of New Signals
2 19-A2 Extract of Schedule of Dimensions (SOD)
3 19-A3 Method for Finding Out the Resistance of an Earth
Note: This Chapter has under mentioned Maintenance Schedules in Appendix-I
S.No. Annexure No. Description
1 19-MS1 Maintenance Schedule of Colour Light Signal
Maintenance Schedule of Electrically Operated Points (Inclusive
2 19-MS2
of Clamp type Point)
3 19-MS3 Maintenance Schedule of Electrical Point Detector (EPD)
4 19-MS4 Maintenance Schedule of Key Locked Checking Relay/Electric Key
Transmitter (KLCR/EKT)
5 19-MS5 Maintenance Schedule of Fuses & Fuse Alarm System
6 19-MS6 Maintenance Schedule of Earthing and Lightning Protection
Note: This chapter has under mentioned Drawings in Appendix-II
S.No. Drawing No. Description
1 19-D1 Apparatus Case Full Size Foundation
2 19-D2 Apparatus Case Half/Quarter Size Foundation
3 19-D3 Main Signal Post Foundation
4 19-D4 Shunt Signal Foundation
5 19-D5 Drawing of Earthing for S&T Installation
6 19-D6 Earthing Arrangements for Signals, Location Boxes
7 19-D7 Copper Plate Earthing Arrangement
8 19-D8 Full Location Wiring Format
9 19-D9 Half Location Wiring Format
10 19-D10 Signal Markers & Number Plates
Chapter 19: Installation, Testing & Maintenance of Signalling Equipment Page 414 of 535