Section 9: Maintenance of Power Supply Equipment
16.9.1 (a) Change-over panel in ASM office shall be kept in good working condition.
Defects, if any, shall be advised to Electrical Department for prompt
rectification.
(b) The working of power supply modules like DC-DC converters, voltage regulator
transformer, battery charger rectifier, inverters etc., provided in power
equipment room shall be checked including proper working of switches, fuses,
MCBs, SPDs, terminals, meters etc. during scheduled maintenance. Units shall
be switched from active to standby as per local instructions.
(c) The power equipment shall be cleaned by blower or any other suitable
device to remove dust etc.
(d) The wiring shall be checked to ensure that wires are in good condition and
connections are properly tightened.
(e) Record of voltages and load current of all power equipments shall be
maintained on the prescribed format. Remedial action shall be taken in
case any abnormality is observed.
(f) Insulation of transformers shall be meggered at 500 V annually.
Section 10: Maintenance of DG set
16.10.1 (a) Fuel tank shall be cleaned periodically. Fuel shall be filled through a wire gauge
filter which shall form part of fuel tank. Before filling up, unused fuel shall be
decanted/replaced if the DG set has been idle for a considerable time.
(b) Lubricating oil shall be periodically checked and proper level maintained.
(c) The maintenance of DG set shall be undertaken by qualified and trained
mechanics. During testing of DG set, the maintenance staff shall wear
rubber hand gloves and take necessary safety precautions.
(d) After specified hours of run prescribed by the manufacturer, the diesel
generator sets shall be overhauled by OEM or his authorised
representative or by designated railway staff.
(e) Leakage of fuel oil, lubricating oil and radiator water shall be effectively
checked.
(f) Radiator fan shaft shall be grease lubricated and worn out shafts replaced.
Radiator hose and fuel oil hose shall be checked for leakage and replaced
in time.
(g) Automatic starting device, where provided, shall be tested periodically for
effective starting during power failures and low voltage condition.
Chapter 16: Power Supply Systems for Signalling Installations Page 329 of 535