(g) Power supply equipment shall be installed in a Gate goomty. In RE areas,
                           Up AT, Dn AT in Double line or single AT in Single line shall be provided
                           along  with  local  power  supply.  In  Non-RE  areas,  Local  power  supply,
                           Generator supply, Solar power supply shall be provided.

                        (h) Road user signal shall be provided to indicate whether the gate is closed or
                           open. While closing/opening the Electric lifting barrier, a hooter shall sound
                           and road user signal shall exhibit red. In closed condition of ELB, the hooter
                           shall stop and road user signal shall display steady red. In open condition of
                           ELB, the road user signal shall display steady yellow.

                        (i)  At  least  two  types  of  operations  should  be  provided  i.e.  Power  operation
                           and Manual Cranking operation. Hand Generator operation type may also
                           be provided where feasible.

                                          Section 3: Maintenance of LC Gates


               14.3.1  Maintenance of Mechanical Lifting Barrier (MLB)

                        (a) All moving parts shall be properly lubricated.

                        (b) Gears, rope drums and wire rope shall be doused with soft grease.

                        (c) Cleaning  of  rodding  and  wire  transmission  should  be  done  properly.
                           Cleaning of all pipes and ducts to prevent obstruction by accumulation of
                           dirt shall be ensured.

                        (d) All bolts and nuts shall be tightened and split pins shall be split properly.

                        (e) Worn out pins, if any, in the crank shall be replaced.

                        (f)  It shall be ensured that both the booms are parallel in open condition.


                        (g) Proper adjustment of wire sag and tension shall be made.

                        (h) Integrity of interlocking and boom locking shall be checked.

                        (i)  Rusty wires and rodding shall be replaced.

                        (j)  It shall be ensured that 'E' type lock which locks the winch should also lock
                           winch handle in closed position of barrier.

                        (k) All gate locking apparatus must be examined regularly and working parts
                           kept oiled. Gate locks must be kept in good working order.

                        (l)  Proper working of audio/visual warning shall be ensured.