735. No  work  asked  for  by  another  government  department  should  be  commenced till  a
                 detailed  estimate  for  the  same  has  been  accepted  by  the  department  concerned  and
                 sanctioned by the competent railway authority. No work asked for by local bodies, private
                 individuals,  and  c,  should  be  commenced  till  a  detailed  estimate  for  the  same  has  been
                 sanctioned the competent Railway authority and the estimated cost thereof deposited with
                 the  Railway.  The  amounts  so  deposited  should  be  credited  to  the  head  "Deposits−
                 Miscellaneous" Competency of Sanction.

                 748.  The  previous  sanction  of  an  authority  higher  than  the  General  Managers  of  Indian
                 Railways is necessary:

                      (i)  To  expenditure  on  new  lines  or  rolling  stock  or  surveys  not  provided  in  the
                         sanctioned budget for the year or carried forward from the sanctioned budget of
                         the previous year;


                      (ii)  To expenditure  on other works not provided in the sanctioned budget or carried
                         forward from the sanctioned budget of any previous year except:

                         (a) (i) Track renewal works − costing not more than Rupees two lakhs;

                             (ii) Other works − costing not more than Rupees one lakhs;

                             (iii) Machinery and Plant − costing not more than Rupees Fifty thousands.
                             Provided that the total lump-sum provision made in the budget for such works
                             is not exceeded.


                         (b)  (i)  On  line  capacity works  costing  above  Rupees  one  lakh  but  not more than
                                 Rupees ten lakhs each;
                             (ii)  On track renewal works costing above Rupees two lakhs but not more than
                                 Rupees five lakhs each;
                             (iii) On other than line capacity and track renewal works costing above Rupees
                                 one lakh but not more than Rupees five lakhs each;

                             Subject to ceiling of Rupees one crore in all in a financial year provided that the
                             sanctioned budget (other than lump-sum) for works in these categories is not
                             exceeded.

                      Note: (1) The works thrown forward from previous years may be taken up only if the
                                funds  required  for  them  can  be  found  by  reappropriation  within  the
                                sanctioned allotment.
                            (2) The savings in the lumpsum provision made in the sanctioned budget shall not
                               be utilized for the category of works in (b) above without the prior approval of
                               the Railway Board.
                            (3) The General Manager may sanction expenditure on new works out of turn in
                               respect  of  users'  amenities  including  goods  shed  and  booking  office  not
                               exceeding Rupees one lakh in each case provided the funds required for such
                               works as provided in the sanctioned budget for works in these categories is
                               not  exceeded;  and  expenditure  upto  Rupees  fifty  thousand  in  each  case,  in
                               respect  of  existing  Railway  schools,  institutes,  hospitals  and  dispensaries
                               provided the lumpsum provision in the sanctioned budget is not exceeded.


                                              Chapter 5: Planning, Estimating & Survey            Page 101 of 535