Page 127 - IRSEM_Main Book
P. 127

An abstract of the completion estimate showing the above particulars against the various
                 heads  of  capital  classification  should  be  submitted  for  information  or  sanction,  vide
                 paragraph 1703 to the Railway Board together with brief explanations for excesses of not
                 less than Rs. 10,000 or 10 per cent over the provision under sub-heads of account and for
                 savings  of  20  per  cent  or  one  lakh,  whichever  is  less,  occurring  under  any  main  head  of
                 account. Provision for further outlay should be made in completion estimate only for those
                 works  which  are  in  progress  or  completed  on  the  date  of  closing  of  the  construction
                 estimate. All works not started on that date should be dealt with separately as open line
                 works  both  as  regards  estimate  and  expenditure.  In  forwarding,  therefore,  estimates  for
                 sanction  for  works  in  connection  with  new  lines  opened,  it  should  be  clearly  indicated
                 whether the cost of the work is chargeable to Capital Construction or Open Line Capital.


                Note:  The  completion  estimate  of  an  unremunerative  construction  project  chargeable  to
                      Development  Fund  will  be  prepared  in  the  same  detail  as  the  original  construction
                      estimate using the various heads of capital classification for the purpose.

                 714. Estimates for Railway Project: Scope − A Construction Estimate (Form E. 553) should
                 be prepared in such detail as to reduce to a minimum the probability of omission of any item
                 of expense which is capable of being foreseen. It should be remembered particularly that the
                 provision for contingencies allowed in the estimate is not intended to meet items of expense
                 which  can be foreseen and  which  are  reasonably likely  to occur.  With good estimating it
                 should  seldom  be  necessary  to  encroach, to  any appreciable  extent,  on  the  provision  for
                 contingencies.

                 727. Provision for contingencies: Provision for unforeseen contingencies should be made in
                 all estimates at 3 per cent of the total estimated cost. All incidental expenditure which can
                 be  foreseen  such  as  works  establishment,  sheds  for  workmen  and  stores  should  be
                 separately  estimated  and  provided  for  in  the  estimates.  The  provision  for  contingencies
                 should not be diverted to any new work or repair which is not provided for the estimate, and
                 of which the cost exceeds Rs. 1,000 without the sanction of the authority who sanctioned
                 the estimate.


                 729. Schedule of Rates:  To  facilitate the preparation  of estimates, a schedule of  rates of
                 each kind of work commonly executed should be maintained in each open line division, and
                 it will be the duty of the Chief Engineer when inspecting the divisional offices, to see that
                 correct  schedules  of  the  rates  at  which  work  is  actually  being  carried  out,  are  invariably
                 recorded in a complete and satisfactory manner. The regulations for the due record of rates
                 in a clear and systematic manner and for their periodical revision to bring them on line with
                 the rates prevailing in the market and those paid by other government departments will be
                 laid down by the General Manager.














                                              Chapter 5: Planning, Estimating & Survey            Page 99 of 535
   122   123   124   125   126   127   128   129   130   131   132