(v) Abnormal  disappearing  of  train  describer  tag  shall  generate  an  alarm
                               and display in different colour.


                        (d) Control Function:

                        After  taking  control  of  an  area,  the  central  controller  will  be  able  to  send
                        commands to the corresponding interlocking. The possible commands are:

                            (i) Setting/cancellation of route.

                            (ii) Moving point to Normal or Reverse.

                            (iii) Controlling signal (ON/OFF) as permitted by interlocking.

                            (iv) Setting/cancellation of traffic & power block.


                            (v) Turning the ARS mode ON/OFF, long route setting & route stacking.

                            (vi) Loading of Timetable/Train Chart.

                        (e) Automatic Route Setting (ARS):

                            (i)  The automatic route setting feature will be possible to be provided for
                               identified stations/routes/sections.

                            (ii) The ARS system relieves the operator from repetitive route setting tasks
                               for the  trains  at  these  stations and the operator can monitor the  train
                               operation  from  OCC  (Operation  Control  Centre).  The  system  shall
                               execute the commands according to timetable.

                        (f)  Long  Route  Setting  &  Route  Stacking:  The  chief  controller/section
                           controller  in  OCC  can  set  long  route  for  one  station  to  another  station.
                           Provision of Route stacking shall be made to set routes of multiple trains in
                           advance.

                        (g) Block Working Operation:

                            (i)  Block Operation for EI station will be done through CTC controller from
                               OCC. Suitable failsafe provision of inbuilt block operation system in EI is
                               needed  for  this  and  Conventional  block  instrument/panel  may  not  be
                               used  for  block  operation.  In  case  inbuilt  block  working  in  EI  is  not
                               available,  local  operation  of  block  instrument  will  be  done  by  SM  at
                               station.

                            (ii) For PI/RRI stations operation of block instruments/block panel may be
                               required to be done by SM at station.