(6) The expenditure on each work shall be limited to the sum allotted for it. If for exceptional
                    reasons,  expenditure  in  excess  of  Budget  allotment  has  to  be  incurred  and  if  the
                    authority  incurring  the  expenditure  is  either  not  in  a  position  to  find  funds  by  re-
                    appropriation or is not empowered to sanction a re-appropriation thereof, application
                    for  additional  funds  shall  be  made  to  the  next  higher  authority  slating  how  the
                    expenditure is proposed to be met. In doing so, it should invariably be explained why the
                    need for the expenditure was not foreseen in time for inclusion in the Budget and why
                    the outlay cannot be postponed to the next financial year. In each case a copy of the
                    order  making  the  allotment  or  sanctioning  a  re-appropriation  shall  be  sent  to  the
                    Accounts  Officer  concerned  by  the  authority  issuing  the  order  or  sanctioning  the  re-
                    appropriation. (Para 368)

                (7)  Responsibility  of  Railway  Administrations  in  case  of  Excesses  of  Lapses:  The  Railway
                    administrations shall be responsible to ensure that no expenditure is incurred in excess
                    of the Budget allotments made to them. Should it become apparent at any time that the
                    grant  for  the  year  is  likely  to  be  exceeded  from  any  cause  whatsoever,  the  General
                    Manager should report the position to the Railway Board and apply for additional funds.
                    No liability may be incurred in one year against anticipated grants of a succeeding year
                    except that advance commitments for procurement of stores for works may be made as
                    provided in para 812-S to the extent authorised by the Railway Board from time-to-time.
                    (Para 371)

                (8) It shall also be the duty of the administrations to see that the allotments made to them
                    are fully expended, in so far as in consistent with economy and the prevention of large
                    expenditure in the last months of the year for the sole purpose of avoiding lapses. They
                    shall be responsible for ensuring that money which is not likely to be needed during the
                    year is promptly surrendered so as to allow of its appropriation for other purposes. (Para
                    372)

                (9)  Powers of Railway Administrations in regard to emergent and inevitable expenditure:
                    Notwithstanding  the  provisions  of  paragraph  7  above,  the  commencement  of  works
                    urgently necessary to safeguard life or property or to repair damage to the line caused
                    by  flood,  accident,  earthquake  or  other  unforeseen  contingency,  so  as  to  restore  or
                    maintain through communication may be authorised by the Executive Engineer, but he
                    should at once submit a report through the usual channel to the authority competent to
                    give administrative approval to the work and to allot the required funds. (Para 373)

                (10) Expenditure to meet a sudden increase in traffic or for ensuring the safe operation of
                    traffic  may  be  incurred  with  the  personal  sanction  of  the  General  Manager  in
                    anticipation of the allotment of necessary funds by the Railway Board provided that the
                    Financial Adviser and Chief Accounts Officer concurs. This power cannot be delegated
                    and can be exercised by the General Manager only where the expenditure is within his
                    power of sanction. In all cases where this requires an allotment of additional funds, a
                    report showing the expenditure  involved  and the additional funds required should be
                    submitted to the Railway Board, as soon as possible. (Para 374)