Page 103 - IRSEM_Main Book
P. 103

Para No. 4.3.3(b)                                                             Annexure: 4-A9

                        Register of Works is a Collective Record of Expenditure Designed
                                       (Extract of Indian Railways Engineering Code)

                 (1) Register of works is a collective record of expenditure designed:

                    (i)  for  effecting  control  of  expenditure  on  works  with  reference  to  estimates,  by
                        facilitating  comparison  between  the  expenditure  incurred  on  each  work  and  the
                        detailed provision made in the estimate for work; (Para 1472)


                    (ii)  for  effecting  budgetary  control,  by  facilitating  a  comparison  between  the  budget
                        allotment for the work and the actual expenditure to the end of the month; and


                    (iii) to enable any material modification occurring being spotted.

                 (2)  Single  set  of  works registers: Detailed  Register  of  Works in  form  E-1473  given  below
                    should  be  kept for  all  sanctioned  works  including  those  chargeable to Revenue,  'New
                    minor  works',  showing  the  amounts  of  estimates  sanctioned.  This  register  shall  be
                    maintained  in  the  Accounts  Office  both  for  open  line  and  construction  organisation.
                    (Para 1473)

                                                    ………………….. RAILWAY                           Form E-1473

                                                     WORKS REGISTER

                 Name of work……………………………………………………………………………

                 Authority…………………………………………………………………………………


                 Capital………………………………………...Rs. Cash ……………………………..Rs.

                 Depreciation Fund…………………….............Rs. Stores ……………………………Rs.

                 Development Fund……………………………Rs. Total ……………………………..Rs.


                 Accident compensation Passenger

                 Amenities Fund……………………………………………………………………………

                 Open Line Works-revenue…………………………………………………………….….


                 Revenue…………………………………………………………………………………Rs

                 Date of commencement…………………………………………………………………...

                 Date of completion……………………………………………………………………….


                 Budget Allotment for the year…………………………………………………..............Rs

                 Original estimate No………………………………………………………………………

                 Revised Estimate No………………………………………………………………………


                              Chapter 4 Budget Estimates, Expenditure, Budget Control and Completion Reports   Page 76 of 535