Para No. 4.1.6                                                                       Annexure: 4-A1

                                             Powers of the Railway Board
                             (Extract of Chapter III of Indian Railways Financial Code, Volume I)

                 (1) Powers of the Railway Board: Within the amount of a grant as voted by the Parliament,
                    the Railway Board have full power of transferring the provision from one sub-head to
                    another by a formal order of re-appropriation but re-appropriations, from one grant to
                    another  are  not  permissible.  Under  Grant  No.  16  no  re-appropriation  of  funds  is
                    permissible between Capital, Railway Funds and Revenue even though re-appropriation
                    is  permissible  between  the  various  sub-heads  of  grant  viz.,  the  various  plan  heads.  As
                    regards "Charged" expenditure there  are  no  restrictions  on  the  powers  of  the  Railway
                    Board  to  transfer  provision  from  one  sub-head  to  another  by  a  formal  order  of  re-
                    appropriation  but  no  re-appropriation  is  permissible  from  one  grant  to  another  from
                    "Charged" heads to "Voted" heads or Vice Versa. (Para 376)

                 (2) Powers of Railway Administrations: No re-appropriation is permissible between "Voted"
                    and "Charged" allotments or between the allotments made under one grant and another.
                    In the case of Grant No. 16 no re-appropriation is permissible between the Capital Railway
                    funds and revenue. The re-appropriations. (Para 377)

                    (a) to and from the provision for the following plan heads under Grant No. 16:
                       (i)  New Lines (Construction);
                       (ii)  Gauge Conversion;

                       (iii) Electrification Projects;
                       (iv) Track renewals;
                       (v)  Staff quarters          }    Staff Welfare Works.

                       (vi) Amenities for staff }    Staff Welfare Works.
                       (vii) Passenger Amenities and other Railway Users' amenities.

                    (b) to and from the provision for "Payments to other Railways" in Grant No. 9, and;
                    (c) to and from the provision for "Suspense" in Grant No. 12 requires prior approval of
                        the Railway Board.

                 (3) The amount allotted to the Railway administrations under the Civil Grant for "Interest on
                    debt and other obligations and reduction or avoidance of debt" is distributed under the
                    following units of re-appropriations, viz.,
                    (a) State Provident Funds;
                    (b) Railway Staff Benefit Fund;

                    (c) Eastern Group Sleeper Control Provident Fund;
                    (d) Indian Railways Conference Association Employee's Provident Fund;
                    (e) Depreciation Reserve Fund, Railways;
                    (f)  Revenue Reserve Fund;

                    (g) Railway Development Fund;
                    (h) Accident Compensation, Safety and Passenger Amenities Fund, and

                    (i)  Pension Fund.
                    No re-appropriation is permissible from one unit to another.