Page 518 - IRSEM_Main Book
P. 518

Note: (i) FAT should preferably be conducted at factory premises. However, FAT can
                              also be done at railway premises at central location but not at the site. For this,
                              the setup should be made by all the Zonal Railways.
                              (ii) FAT & SAT should be done by separate officials where ever feasible.

                21.5.3  Power Supply for Electronic Interlocking


                        (a)  Adequate redundancy in power supply arrangements for E.I systems including
                            Control  Terminals  shall  be  provided  as  per  approved  specifications  and
                            guidelines.

                        (b)  Wires connecting equipment shall be of adequate size so that there is not
                            more than 0.5% loss in voltage.

                        (c)  The power supply for fan shall be fed with separate external supply, which
                            should  be  completely  isolated  from  Electronic  interlocking  supply  and
                            same shall be provided with fuse.

                21.5.4  Lightning & surge protection, Earthing: Shall be done as per Section 7 of
                        this chapter

                21.5.5  Testing & Commissioning of Electronic Interlocking:

                        Wiring, Testing & Commissioning shall be done as per Para 19.8.5 to 19.8.12.

                        Recommended check list of items for commissioning is given at Annexure:21-
                        A2. This list may be suitably modified as needed.


                                        Section 6: Maintenance of Interlocking

                21.6.1  Periodicity of Tests (for existing installations - Relay interlocking/Electronic
                        Interlocking)

                        All the tests indicated in this chapter shall be conducted at the time of new
                        installation or making any alteration to the existing installations.

                        (a)  In a working installation, the following periodical tests shall  be done:

                            (i)  Physical inspection once in a year or earlier as feasible.

                            (ii)  System integrity test as per para 19.8.8 once in five year or earlier if
                                interlocking is altered.
                            (iii)   Insulation tests on Cables as per Chapter 15 of SEM.


                            (iv)  Test  of  individual  equipment  in  accordance  with  specifications  and
                                instructions  applicable  for  each  apparatus  as  stipulated  in  current
                                Chapter.

                        (b)  It  will  be  personal  responsibility  of  SSE/JE(Signal)  to  test  all  Electrical
                            signalling circuits of relay interlocking up to 20 routes.

                        (c)  It  will  be  personal  responsibility  of  ASTE/DSTE  concerned  to  test  all
                            electrical signalling circuits of relay interlocking with more than 20 routes.