12.27.2  Date of last Overhauling and Testing

                         (a) Date of last overhauling and testing shall be painted on the lever frames,
                             interlocking key boxes and Station Master's slide control frames.

                           Section 28: Testing and Overhauling of  Electromechanical

                                                          Installations

                12.28.1  Mechanical Locking

                         (a) Instructions  contained  in  the  preceding  paragraphs  for  the  installation,
                             maintenance,  overhauling  and  testing  of  locking  of  mechanical  interlocking
                             frames  shall  also  apply  to  electromechanical  installations  with  mechanical
                             locking frames wherever relevant.

                         (b) The  mechanical  locking  of  interlocking  frames  shall  be  tested  for  lost
                             motion,  as  per  para  12.1.3(i)  and  lost  motion,  when  in  excess  of  the
                             prescribed limits, shall be removed.

                12.28.2  Electrical Locking

                         (a) In  electromechanical  installations  electric  lever  locks,  key  transmitters,
                             circuit controllers, Detectors etc. shall be provided as per approved plan.

                         (b) Diagram of electrical circuits for each such gears shall be prepared and
                             shall show all the necessary controls which shall be required to release a
                             particular lever.

                         (c) Where lever locks have been provided in the mechanical lever frames for
                             controlling operation of Electric Point Machine, Electric Signal Machine or
                             for route holding etc the functioning of the same shall be tested.

                             (i)  Points Lever:  In points lever ABDE locks are provided for Track &
                                 Indication locking. Lever shall be tested to ensure that the lever lock is
                                 energised  and  the  lever  is  free  to  be  operated  in  A/E  position  only
                                 when the controlling tracks are clear. The lever shall again be locked
                                 in D position when the point is being operated from normal to reverse
                                 and  lever  shall  be  free  only  when  the  points  has  operated  fully  and
                                 locked and detected in reverse position. Similarly, while operating the
                                 lever from reverse to normal the lever shall be first locked in E position
                                 to ensure track locking and subsequently will be held at B position for
                                 point operation. The lever lock shall not energise at B position unless
                                 the points have operated, set, locked and detected in normal position.

                             (ii) Signal Lever:  While pulling the signal lever from normal to reverse
                                 the lever shall be locked in A position and will be free only when route
                                 for the reception of the train has been correctly set, all facing points
                                 locked  and  all  the  controlling  tracks  are  clear  i.e.  all  conditions  are
                                 fulfilled for taking 'OFF' the signal. While putting back the lever from
                                 reverse to normal position the lever shall be locked at B position and
                                 will be free only when the intended movement is completed and it is
                                 free  from  back  locking  as  well  as  approach  locking  where  provided.
                                 Normal indication locking must also be effective in B position in case
                                 of semaphore signal.